Re: Carriageway Resurfacing  

Temporary Road Closure Map 

 Temporary No Stopping map

Via East Midlands in partnership with Nottinghamshire County Council intends to carry out the carriageway resurfacing on Padleys Lane, Burton Joyce.

Tarmac will be delivering the works for Via East Midlands. The proposed programmed start date is Monday 3rd April 2017 with works planned for a period of 11 days. The programmed dates and works given below are a guide, which can be affected by weather conditions and material deliveries.

Day Date Location Works
1 Mon 3rd April Road closed between Foxhill Road (middle junction) and Main Street.

School access to house number 30

Set up temporary traffic management systems.

Kerbing and footway resurfacing

2 Tues 4th As above As above
3 Wed 5th As above As above
4 Thurs 6th As above As above
5 Fri 7th Padleys Lane full length closed.

School access to house number 30.

Foxhill Road (top junction) to   Brusty Place

 

Kerbing and footway resurfacing.

Carriageway surface removal (35mm average depth), adjust ironwork.

6 Sat 8th Foxhill Road (top junction) to   Brusty Place

Brusty Place to house number 30.

Adjust ironwork.

Carriageway surface removal 110mm depth, lay base layer 60mm depth, adjust ironwork.

7 Sun 9th    
8 Mon 10th Brusty Place to High Street.

House number 30 to Main street.

Adjust ironwork.

Carriageway surface removal 110mm depth, lay base layer 60mm depth.

9 Tues 11th Foxhill Road (top junction) to   Brusty Place. Lay new road surface.
10 Wed 12th Foxhill Road (middle junction) to Main Street. Lay geogrid and new road surface.
11 Thurs 13th Padleys Lane full length and all side junctions. Lay thermoplastic road markings.

Remove temporary traffic management systems.